Sherk and Ellison Intersection Signalization Project

Default Interior

At its March 15, 2022 Council meeting, Leamington Council approved capital improvements to the intersections of Sherk Street and Ellison Avenue.

Project features include:

  • a new traffic signal at Sherk Street and Ellison Avenue;
  • updated street lighting along Ellison Avenue between the trail and Sherk Street;
  • a 3.0m wide concrete sidewalk between the trail and Sherk Street;
  • a PXO at the trail and Ellison Avenue crossing;
  • a dedicated left turn lane on Sherk Street for northbound traffic; and
  • new curb and sidewalk ramps associated with implementing a new signal and sidewalk.

Project Timeline

The project is slated to begin July 4, 2022 and is expected to be completed, weather dependent, by September 16, 2022.

Traffic Disruption

Temporary lane closures will be required throughout the duration of the project.