Sidewalk Construction - Oak Street

Default Interior

The construction of a sidewalk from Fraser Road to Nicholas Street on Oak Street West will commence November 20, 2017.  The sidewalk will link to one of the Transit stops, and provide a link between the existing commercial areas, residential areas and the new Leamington District Secondary School at 80 Oak Street.

When will construction begin and how long?

The sidewalk is to be constructed on the south side of Oak Street West to line up with the sidewalks previously installed at the new Leamington District Secondary School.  Construction is to begin on November 20, 2017 and will take 2 weeks to complete.  In order to complete this work in a timely fashion and increase public safety eastbound Oak Street will be closed from 7am to 7pm daily.  To access businesses along the route you will have to follow the detoured routes and enter from the westbound lane.  