Projects and Studies

Default Interior

 

Development Charges 

The 2022 Development Charges Background Study has been prepared by Watson & Associates Economists Ltd., and is available for review:

Clean Water and Wastewater Fund (CWWF)

The Municipality will complete construction work related to the following six (6) projects that received provincial funding as part of the Clean Water and Wastewater Fund (CWWF) program.  Each of these projects will benefit either the water, wastewater or storm water systems in the Municipality of Leamington. 

Link to Infrastructure Canada

Separation of Sewers on Lorne, Gladstone, Melrose, Henry and William Avenue

This project will include preparation of plans and specifications to obtain approvals necessary for tendering and constructing this sewer separation project.  Works will include sewer, roadway, sidewalk and lighting.  The existing 71 homes are currently serviced by an aging combination sewer that flows downstream to separated sewer system and combined sewer overflows to Lake Erie.  The eligible costs are limited to public/municipal property and assets.  This project is currently in the construction stage and is partly funded through Infrastructure Canada.

 

Total Project Cost - $200,000

Program Contributions (Eligible Expenditures) - $100,000

Provincial Contributions - $50,000

Municipal Contribution - $50,000

Separation of Sewers on Parkdale and Coronation Street
This project will include preparation of plans and specifications to obtain approvals necessary for tendering and constructing this sewer separation project.  Works will include sewer, roadway, sidewalk and lighting.  The project affects 56 homes that are currently serviced by an aging combination sewer that flows downstream to a separated sewer system. The eligible costs are limited to public/municipal property and assets.  This project is now complete and was partly funded through Infrastructure Canada.

 

Total Project Cost - $952,000

Program Contributions (Eligible Expenditures) - $431,000

Provincial Contributions - $215,500

Municipal Contribution - $215,500

Seacliff Trunk Sanitary Sewer Study
This study will provide guidance on the steps and costs to separate and remove combined sewage from the trunk, and provide sewer service to areas along Lake Erie.  As the Seacliff Trunk Sanitary Sewer currently accepts sanitary and combined sewage from the southern portion of Leamington, servicing additional areas is not permitted by the Ministry of the Environment and Climate Change regardless of available capacity.  Once the Seacliff Trunk Sanitary Sewer is fully separated, it will allow for future sanitary servicing of existing homes and properties along Lake Erie that are currently using septic systems.  This study is complete and is partly funded through Infrastructure Canada.

 

Total Project Cost - $102,852

Program Contributions (Eligible Expenditures) - $51,426

Provincial Contributions - $25,713

Municipal Contribution - $25,713

Southwest Leamington Storm Water Management Pond and Outlet Environmental Study and Design
This proposed project is multi-category including wastewater and stormwater components, but primarily stormwater.  The Southwest Leamington Storm Water Management Pond Outlet project will support further separation of storm and sanitary sewers in Leamington by eliminating the continuing need to use an existing asset as a combined sewer.  A new stormwater outlet will: provide enhanced treatment and storage of stormwater, eliminate combined sewer overflows and allow additional sanitary collection and conveyance for the existing and future developments in Southwest Leamington by optimizing an existing asset (conversion of existing combined sewer to dedicated sanitary sewer).  This environmental Study assignment will address enhanced service and improved environmental outcomes by providing the planning solution, preferred alternative and preliminary design for the management of surface water in the southwest quadrant of Leamington.  Particularly, our Study Area comprises approximately 110 Ha, including 25 Ha of existing residential and institutional land uses serviced by aging combined sewers.  The remaining 85 Ha are designated for urban, residential development.  This project has not yet commenced but will be partly funded through Infrastructure Canada.

 

Total Project Cost - $175,000

Program Contributions (Eligible Expenditures) - $87,500

Provincial Contributions - $43,750

Municipal Contribution - $43,750

Reconstruction and Separation of Sewers on Mill Street West
This project will include the completion of plans and specifications, tendering, approvals and construction of this sewer separation project.  Works will include sewers, roadway, sidewalks and lighting.  The project affects the existing 15 small businesses that are currently serviced by an aging combination sewer that flows downstream to a separated sewer system.  The eligible costs are limited to public/municipal property and assets.  This project is now complete and was partly funded through Infrastructure Canada.

 

Total Project Cost - $1,220,000

Program Contributions (Eligible Expenditures) - $401,880

Provincial Contributions - $200,944

Municipal Contribution - $617,168

Separation of Sewers on Danforth Avenue
Preparation of plans and specifications to obtain approvals necessary for tendering and constructing this sewer separation project.  Works will include sewers, roadways, sidewalks and lighting.  The project affects the existing 65 homes that are currently serviced by an aging combination sewer that flows downstream to a separated sewer system.  The eligible costs are limited to public/municipal property and assets. This project is now complete and was partly funded through Infrastructure Canada.

 

Total Project Cost - $2,840,000

Program Contributions (Eligible Expenditures) - $1,222,112

Provincial Contributions - $611,056

Municipal Contribution - $611,056

 

Canada Community-Building Fund
LED Street Light Conversion

The conversion to LED Bulbs in our street lights will allow for a longer useful life and allow for a large saving in energy consumption.  LED lights contain no toxic chemicals and are 100% recyclable allowing us to reduce our carbon footprint.  LED lights brighten up immediately and when powered on, has great advantages for infrastructure projects such as Streetlights.

 

Total Project Cost - $1,300,000

Cumulative CCBF Funds - $1,150,000

Local Roads and Bridges

 

Current Projects
2023 Road Resurfacing
The Municipal road reconstruction / modification program allows for the hard surfacing of gravel roads and the reconstruction of existing pavement surfaces. The new hard surfaces allow for a smoother ride and less maintenance which will add to the reduction in Green House Gas.

Total Project Cost - $1,780,000
Total Cumulative CCBF Funds - $280,000
Bridge 37
This project is for the engineering and reconstruction of bridge #37 on Deer Run Road. The replacement of this bridge is identified as a high priority in the Municipality's 2019 Bridge Condition Survey.

Total Project Cost - $710,075
Total Cumulative CCBF Funds - $50,000
Bridge 71 and 77 
Engineering and design and approvals for the rehabilitation of bridges 71 and 77 where the 2021 Biennial Bridge and Culvert condition survey determined that the existing structures are in need of rehabilitation.

Total Project Cost - $120,077
Total Cumulative CCBF Funds - $65,077
Erie Street Between Clark and Marlborough
In October 2018, Council approved, in principal, the Leamington Uptown Master Plan as the basis for future infrastructure improvements and beautification in Uptown Leamington. It is proposed to begin assignment, in preparation for future construction, and apply the Plan in the vicinity of Erie Street, between Clark and Marlborough Street. 

Total Project Cost - $250,000
Cumulative CCBF Funds - $250,000
Erie Talbot Streetscaping
In October 2018, Council approved the Leamington Uptown Master Plan as the basis for future infrastructure improvements and beautification in Uptown Leamington. Work will begin with a design assignment in preparation for future reconstruction and streetscaping complete with new sidewalks, curbs, street lighting, bike lanes and other appurtenances. The project will reconstruct the two main corridors through our uptown core (1.1km).

Total Project Cost - $3,050,000
Cumulative CCBF Funds - $750,000
Sidewalk Construction (Ellison)
The Municipality is constructing a new 190m sidewalk. This sidewalk connects the busiest section of the municipal trail network to additional bike lanes and provides for the growth and expansion of our active transportation network.

Sidewalks create a number of positive beneficial aspects for a community and correspondingly, sidewalk deficiencies create a number of challenges. The location for new sidewalk works are established based on the Sidewalk Priority and needs of the Community.

Total Project Cost - $122,500
Cumulative CCBF Funds - $122,500
Completed Projects
Bridge 21
The engineering and reconstruction of Bridge #21 on Mersea Road 7. The replacement of this bridge is identified as a high priority in the Municipality's 2019 Bridge Condition Survey.

Total Project Cost $545,000
Cumulative CCBF Funds - $545,000
Coronation Sewer Separation / Road Reconstruction
This project involves the separation of sewers to improve sewage collection along the full length of Coronation Avenue (400m), application of new asphalt pavement, and installation of curbing, sidewalks, and upgraded street lighting.

Total Project Cost - $1,065,973.35
Cumulative CCBF Funds - $900,000
County Road #20 Multi-Use Trail
Construction of a hard surfaced multi-use trail from Essex County Road #31 to Sherk Street along the road allowance of Essex County Road #20. The hard surface multi-use trail will give local residents and visitors a safe and enjoyable alternative to motorized vehicles.

Total Project Cost - $2,506,500
Cumulative CCBF Funds - $1,510,000
County Wide Active Transportation System
The County Wide Active Transportation System was a County wide initiative designed to connect the seven lower municipalities throughout the County of Essex. The installation of active transportation routes will provide a safe active transportation system for users of all ages and abilities to actively move around the County of Essex. The facilities being constructed are trails, multi-use paths, bike lanes/cycle tracks etc. 

Total Project Cost - $223,000
Cumulative CCBF Funds - $153,000
Erie Street Sewer Separation / Road Reconstruction
Sewer separation and complete road reconstruction of Erie South, Stewart, Conover Avenue and Forest. This project involves the complete sewer separation and road reconstruction including utility relocations and new road, curb, sidewalks, bike lanes, traffic calming and streetscaping.
This project was partially funded through the Small Communities Fund (SCF). This funding program is made up of shared funds through the Federal Government and Provincial Government for funds up to $4,000,000.

Total Project Cost - $5,695,000
SCF Funds - $4,000,000
Cumulative CCBF Funds - $787,533.79
Henry, Lorne, Gladstone, William and Melrose Sewer Separation
The complete reconstruction of five streets lying east of the Nature Fresh Farms Recreation Center (Henry, Lorne, Gladstone, William, Melrose). Work involves the installation of new storm and sanitary sewers, watermains, roads, sidewalks and streetlighting. 

Total Project Cost - $4,421,000
Cumulative CCBF Funds - $1,370,000
Implementation of Pedestrian Crossings
This project involves installing new pedestrian crossovers, new signage or rapid rectangular flashing beacons at our existing pedestrian crossings. A study to determine the need for pedestrian crossovers at various locations throughout the Municipality. The implementation of Active Transportation Facilities in accordance with the Municipality's Active Transportation Plan.

Total Project Cost - $1,855,000
Cumulative CCBF Funds - $1,855,000
John Street Sewer Separation and Road Reconstruction 
The John Street Sewer Separation and Road Reconstruction is the next step in the municipalities ongoing sewer separation and road reconstruction program. The final outcome of the project will include a new separated sewer, an expansion to the local park, a redesign of the uptown parking lot, and new street lighting and other appurtenances. 

Total Project Cost - $2,585,000
Cumulative CCBF Funds - $463,000
Mill Street Sewer Separation and Road Reconstruction
This project will turn Mill Street into a walkable destination location for uptown events, night markets, street parties, sidewalk sales and more, encouraging residents and visitors to enjoy the daily services of our uptown businesses. Traffic signals at the intersections of Mill Street with Erie Street and Fox Street will be reconfigured. Approximately 300m of storm sewer, 275m of sanitary sewer, and 200m of watermain - along with new sidewalks, benches, planters and LED streetlights - will be installed. 

Total Project Cost - $3,028,463
Cumulative CCBF Funds - $116,000
Seacliff Drive - Cherry Lane to Regatta Road Reconstruction

The purpose of this project is to reconstruct the road to allow for future traffic growth. The project will be completed in phases. The first phase will be the installation of a traffic signal and required road works at the intersection of Cherry Lane and Seacliff Drive. The second phase will be to complete the widening of Seacliff Drive to Regatta, complete with active transportation paths and sidewalks.


Total Project Cost - $3,254,500
Cumulative CCBF Funds - $1,800,000

Traffic Signal Installation at Multiple Intersections
The intersection at Oak & Wigle was identified to have high volumes of pedestrian traffic during peak traffic hours travelling between the residential areas to the north of Oak and the two elementary schools located to the south. The intersection of Erie and Clark has been identified for operational concerns, primarily due to poor sight lines associated with the located of the building on the northwest corner of this intersection. Our fire hall and police station are located on Clark Street.

Total Project Cost - $600,000
Cumulative CCBF Funds - $562,109.77
Completion Date: 
Traffic Signal Installation - Sherk and Ellison
The intersection of Sherk and Ellison has high volumes of traffic during peak hours. The Municipality is therefore installing new traffic signals at this intersection.

Total Project Cost - $500,000
Cumulative CCBF Funds - $500,000
Traffic Signal Upgrades (LED Conversion)

The conversion to LED Bulbs in our street lights will allow for a longer useful life and allow for a large saving in energy consumption.  LED lights contain no toxic chemicals and are 100% recyclable allowing us to reduce our carbon footprint. LED lights brighten up immediately and when powered on, has great advantages for infrastructure projects such as traffic and signal lights.

Total Project Cost - $100,000

Cumulative CCBF Funds - $52,306.64

Canada Healthy Communities Fund

The Municipality of Leamington was funded $35,000 from the Federal Government’s Canada Healthy Communities Fund for the expansion of the Seacliff Park concession patio which includes accessible seating.

Seacliff Park Patio SeatingSeacliff Park Patio SeatingSeacliff Park Patio Seating










CHCI Logos

Margaret St., Audrey St., Jane St., Claire St., and Sherk St. Sewer Separation and Road Reconstruction

As part of the Municipality of Leamington’s continued effort to separate combined sewers; Margaret, Audrey, Jane, Claire and Sherk Street make up the streets in the next steps of the program. The project generally involves the reconstruction of the roads, sidewalks, sewers and street lighting. 

This project is partly funded through the Investing in Canada Infrastructure Program- Green Infrastructure Funding (ICIP-Green)

The ICIP is a federal infrastructure program designed to create long-term economic growth, build inclusive, sustainable and resilient communities and support a low-carbon economy.

Through ICIP, the federal government is providing $11.8 billion in federal infrastructure funding to cost-share projects under the following four streams:

  • Public Transit
  • Green Infrastructure
  • Community, Culture and Recreation
  • Rural and Northern Communities

The Green stream includes up to $7.12 billion in combined federal ($2.85 billion), provincial ($2.35 billion) and other partner ($1.92 billion) funding over 10 years for projects across three federal sub-streams that advance outcomes associated with climate change mitigation, environmental quality and disaster mitigation. It is anticipated that the province will select projects for funding through multiple application intakes.

The Program Contributions (Eligible Expenditures) - $2,172,150

Federal Contributions -  $868,860

Provincial Contributions - $723,978

Municipal Contribution - $579,312

Northeast Trunk Sanitary Sewer

The Municipality of Leamington has completed a Municipal Class Environmental Assessment (EA) study (update to 2006 EA study) for a new 16 kilometre sanitary trunk sewer that will service approved growth areas along MTO Highway 77 and County Road 33.  The Municipal Class EA study has been completed in accordance with the Schedule “B” planning process under the Municipal Engineers Association Municipal Class EA document.

The Project File documenting the Class EA planning process is available for public review and comment for a period of 45 calendar days starting on December 12, 2018 and ending on January 25, 2019.

Northeast Sanitary Trunk Sewer Municipal Class Environmental Assessment

Pump Station #200

The Municipality of Leamington has retained RC Spencer Associates Inc. to complete the Class Environmental Assessment (EA) for the relocation and upgrading of the existing sanitary sewage pump station No. 200 located on Robson Road at Bruce Avenue. The relocation and upgrading is being evaluated due to the need for renewal of the existing pump station infrastructure. 

Service Delivery Reviews

Development Approvals Process Review

In May 2022, the Municipality engaged StrategyCorp to conduct a comprehensive Development Approvals Review Process (DARP) for the Development, Planning and Building Departments. The primary objectives of the review were to:

  • Engage stakeholders, both internally and externally;
  • Assist in identifying challenges within the current development approval processes;
  • Provide core qualities of an effective and efficient development approval process; and,
  • Provide opportunities to address challenges while improving the efficiency and effectiveness of the process.

Development Approvals Review Process Summary (PDF)

Records and Information Management System (RIMS) Review
The Records and Information Management System (RIMS) Review Project was initiated to review the Municipality’s RIMS with the goal of making recommendations to modernize, standardize, improve, and build upon the RIMS based on best practices, costs savings, and efficiencies. The Municipality engaged Ergo Information Management Consulting to conduct the review and prepare a detailed plan and timeline for implementing the recommendations. Ergo will present the findings and final report to Leamington Council on February 14, 2023.

Smart Water Meter Network Project

Leamington Smart Water Meter Network Project Update

The smart water meter network project is 98% complete with approximately 225 meters left to replace.  The Municipality will be working on these meter exchanges over the upcoming months with an estimated completion date of December 2020.  If your meter is located indoors and has not been replaced yet, please contact Leamington Water Services at 519-326-4454 as soon as possible to schedule an appointment.

The majority of installed meters are communicating reads and alerts to municipal staff daily, however, there are a few meters that are not communicating.  Water Services staff have initiated site visits to troubleshoot the meters that are not communicating.  If your meter is located indoors and the issue cannot be resolved from the exterior of the home, Water Services staff will leave a notice on your door to make an appointment.  We ask that you contact Water Services as soon as possible so that we can rectify the communication issue.  We will follow municipal COVID-19 policies and procedures for conducting site visits, and will ask the customer to answer pre-screening questions before entering the home.

We would like to remind Leamington water customers that the purpose of the smart water meter network is to provide real-time data to the Municipality for billing purposes and to provide alerts to help identify possible leaks or flow problems at a customer location.  If the meter and/or radio transmitter are not communicating, the Municipality cannot obtain this critical information. 

During recent site visits, municipal and contractor staff have noticed radio transmitters that have been removed or damaged.  Radio transmitters located in pits have been observed to be covered in dirt, grass, stones or landscaping and some have been sheared off by lawnmowers.   Radio transmitters located on exterior walls of a building have been found to be removed, hanging freely or damaged.  If this happens, the meter cannot communicate to the Leamington network.  Leamington Water Services is asking customers to please take care of this equipment and know where it is located on your property.  Pictures of the radio transmitters are provided below so that customers know what to look for.  Any questions should be directed to Leamington Water Services at 519-326-4454.

 

           Picture of a wall mounted radio                                     picture of outdoor pit radio                                                 picture of an outdoor pit with radio installed

                 Wall Mounted Radio                                           Outdoor Pit Radio                                           Outdoor Pit wit Radio Installed

  

 

In 2019, the Municipality of Leamington will be completing a project to install a new smart water meter network to improve the efficiency and reliability of the water system. KTI Utility Services (KTI) has been contracted by the Municipality to carry out the water meter and radio transmitter installations.

The project includes the installation of new smart water meters and an advanced metering infrastructure (AMI) system comprised of radio transmitters and network components.  The AMI system will provide real-time meter reading data to the Municipality to help identify possible leaks or flow problems and help ensure bill accuracy to avoid unnecessary water costs.

This is a mandatory program in which all customers will require the installation of a radio transmitter.  Customers with water meters more than five years old, or not capable of integrating with the smart meter network, will also require a water meter replacement.

There will be no cost to the customer for the equipment or the installation. Participation in this program is mandatory.

      

Frequently Asked Questions

Why do we need new water meters?

The majority of the meters in the Municipality were installed in 1996 and have a typical life of 10-20 years. The existing meters will be replaced with new water meter technology which is compatible with the latest meter reading technology that offers benefits such as improved customer service, system operation and environmental benefits.

The meter technology currently installed at your home/business will determine if your water meter must be replaced. Not all properties will need to have their water meter changed, however a new radio transmitter will need to be installed at all properties.

What is a water meter? How does it differ from a transmitter?

A water meter is a device that records water consumption. Your water meter is connected to a transmitter, which takes consumption information and sends (transmits) it to a remote reading device that collects this data. This information is then used for billing purposes.

Residential Meter                           Commercial Meter 1.5 to 2 inches                         Commercial Meter greater than 2 inches

Residential Meter                                            Commercial Meter 1.5 to 2 inches              Commercial Meter greater than 2 inches

 

 

                                Non Pit transmitter                                          Pit Transmitter

                                Non-Pit Transmitter                                                              Pit Transmitter

Is this appointment mandatory?

Yes. All customers that have an indoor water meter must schedule an appointment to have a radio transmitter installed and depending on the age and state of your water meter, your water meter may also require replacement. For those customers that have a water meter installed in an outdoor pit, no appointment will be necessary to install the radio transmitter and/or new water meter.

When do I have to book my appointment?

KTI Utility Services will notify customers when they are booking appointments in your area. You will receive a letter from KTI outlining the process of booking an appointment. When you receive your letter, please schedule your appointment as soon as possible to ensure the project remains on schedule.

How do I book an appointment?

As soon as you receive your letter in the mail from KTI, you can book an installation appointment.

 

To book an appointment online:

     1. Click the "book your appointment" button above.

     2. Enter your address, city, postal code and account number. Your account number is located on the appointment notice directly below

         your address details in the top left corner.

     3. View available appointments and book your preferred time slot. At the time of booking, a confirmation will be provided and 

         your appointment details will be emailed to you.

 

To book an appointment by phone:

     1. Call 1-833-543-8807 (toll free) to arrange for your installation appointment. Appointments can be booked by phone

         Monday to Friday from 8:30 AM to 5:00 PM.

How long does the installation appointment take?

Installation of the new meter and radio transmitter normally takes between 30 and 60 minutes.

Do I need to do anything to prepare for the installation?

To help keep everyone safe, dogs and any other domestic pets will need to be kept out of yards during installation. In addition, always keep your meter box lids unobstructed as outdoor installations will be completed without requiring an appointment.

How will I know when the installation is taking place?

This project will take up to 9 months to complete. A letter will be sent to customers between one to two weeks prior to installation in their area. The letter will include instructions on how to book an appointment or indicate that no appointment is necessary.

I've noticed something hung on my door. What is it?

KTI uses a variety of methods to communicate with homeowners and door hangers is one of them. Door hangers will be used to update you on the status of your installation, whether you still need to book your appointment or that you have missed a scheduled appointment. It is important to read your door hanger carefully to know what actions you need to take.

Where is my water meter?

The water meter for your home could be indoors or outdoors in a pit/chamber. If it is indoors, the meter is typically found in the basement or a crawl space, near the main water shut-off valve where your service line comes into your home. If you are having trouble locating the water meter you may want to check your furnace room, utility room or near your hot water tank. 

If the entry to your water meter is less than 3 feet from floor to ceiling, the installer's body needs to enter the limited space to complete the job. It is important to let KTI know beforehand if a crawl space is involved. This will help the installer come prepared so that the required safety protocols are in place while the work is being completed.

Where can I find my water shut-off valve?

Your water shut-off valve is located where your water service line comes into your home, typically in your basement or crawl space.

How much space around the meter does the installer need to complete the work?

The installer will require a clear walking path to the meter area, as well as enough space to kneel down comfortably in front of the meter, with a small tool bag at his or her side.

My water meter is installed behind drywall. How can I ensure the meter is accessible?

 

To remove your current water meter the installer will need to loosen the nuts on either side of the meter using a pipe wrench or a pair of channel locks.  In order to do so, a 15”x15” access hole is required.  KTI installers are trained to cut into drywall neatly and precisely.  Once the installation is complete, this hole can be covered using an access panel that can be found at most hardware stores.  

        access opening                      access panel

What kind of work is involved on the outside of the house?

The new water meter will be connected by a wire to a transmitter on the outside of the home/place of business.  Once the meter and transmitter are installed, Leamington Water Services can obtain transmitted consumption data using reading equipment, without entering your home.  If you have an outdoor pit meter, the transmitter will be installed within the pit application. 

I live in an older home with original plumbing. Do your installers work on old pipes?

Prior to commencing any work the installer will inspect the plumbing to ensure that it is in suitable condition.  If it is determined that the plumbing is not in good enough condition, the installer will provide recommendations to the customer and Leamington Water Services.
Will the installers come inside my home or business for the installation

Yes.  If your water meter is located inside, the installer will enter the home or commercial building to replace the meter and/or change the wiring that connects the meter to the transmitter.  The transmitter will typically be installed outside of the home or business.  The full scope of work will be determined by the installer and communicated with you prior to commencing work.

In commercial settings, the installer will be conducting pre-installation site visits to determine the scope of work for each property.  Following the site visit, an installation appointment may be booked to complete the work.

Will an installer ever show up to my house without an appointment?

Yes, it is possible.  If an installer is in your area and the Municipality has granted KTI authorization, he/she may attempt to knock on your door and offer to do an installation with no scheduled appointment.  If you are uncomfortable with this situation, simply tell your installer you would rather schedule an appointment.

How much will this upgrade cost me?

There is no charge for the new water meter, the radio transmitter or the work to install them at your home or business.

Is the radio frequency created by the new technology safe?

Yes. The new water meters will not negatively affect health or privacy. In fact, overall health will be improved and privacy enhanced by replacing vehicles and manual visits to your home with environmentally clean radio communication.

The wireless portions of the system will be operated according to Federal Communications Commission rules and will not interfere with other radio frequencies in the area. The transmitters emit less radio frequency energy than many other commonly-used wireless devices, like cell phones, baby monitors, satellite TV's, and microwaves that are used daily by millions of people. Radio frequency moves through space at the speed of light. The new water meters use low-energy radio frequency waves to transmit information across distances. Transmission time for the units being installed is less than one second per day.

The World Health Organization and Health Canada are a few of the many credible authors of research studies showing no adverse effects from these radio frequency waves. The California Council on Science and Technology is another excellent source.

Is my account information and meter data secure?

Access to account information is restricted to authorized Leamington municipal staff, who need the data to perform important functions, including improving billing and customer service. The transmitter that sends your meter reading has a unique identifier that is transmitted along with the read data. This identifier is compared electronically to your account record to ensure that the meter reading matches the meter assigned to your account. No customer-identifying information such as names and addresses are stored in the meters or transmitted across the network.

With the new meter technology comes more water consumption data. Just like the old water meters, the new meters collect how much water you use. The main difference is the new meters collect more data throughout the day. Protecting your data is top priority. Using the same advanced methods as internet banking and ATM machines, the new water meter reading system uses proprietary protocols and encryption for your water usage data to ensure privacy, transmitting it to Leamington Water Services over a wireless network with multiple layers of security incorporated throughout the system.

Security measures are tested are reviewed regularly to guard against unauthorized access.

Who do I call if I have questions about the meter installation?

It there are any questions or concerns with the installation process, contact KTI Utility Services at 1 833 543 8807 Monday to Friday 8:30 AM to 5:00 PM.

How can I verify my installer's identity? 

KTI employees can be identified with a KTI uniform, identification badge and will be driving vehicles with the company name and logo. The ID badge resembles the following:

KTI Identification Badge

What kind of technical background and training does my installer have?

Installers completing residential installations will be licensed plumbers and/or certified Water Meter Installers per the 800A apprenticeship program. Commerical installations will be completed by licensed plumbers only.

Is the installer bonded?

Yes. In addition, KTI performs criminal background checks on all installers.

Are other communities pursuing advanced metering infrastructure projects?

Many water utilities in North America are moving to AMI technology including the Town of Lasalle, Municipality of Chatham-Kent, Region of Peel and the City of Toronto.

What is the timeline for the project?

The meter and radio transmitter installation is scheduled to begin in January 2019 and continue for a period of 9 months. The system should be fully operational by the fall of 2019. 

What is the cost to the Municipality of Leamington?

The projected capital cost of the water meter replacement and advanced metering technology project is $3.8 million.

 

Southwest Leamington Stormwater Management Project

The Municipality of Leamington initiated a study to improve municipal drainage infrastructure in Southwest Leamington to support development in the area. The study will consider current drainage challenges, upgrades required and new infrastructure. 

A combined sanitary and stormwater sewer currently collects both household sewage and rainfall runoff within the existing developed area of Southwest Leamington. This study will also evaluate the potential to separate the sewers, which has a number of environmental and cost benefits.

Southeast Leamington Graduated Risk Floodplain Mapping Project

The Municipality of Leamington has retained Zuzek Inc., and their sub-consultants SJL Engineering Inc. and Foresight Management Consulting, to complete a Floodplain Study for Southeast Leamington that accounts for the influence coastal storms and climate change. The study area includes the flood prone lands between Wheatley Harbour to the northern border of Point Pelee National Park, and the west shore to Sturgeon Creek. 

This investigation will study the influence of climate change on future coastal hazards due to changes in storms and ice cover and the associated challenges for the coastal communities of Leamington. Updated floodplain mapping will be generated, along with adaptation options to address the coastal hazards. The ultimate goal is to increase the resilience of the Southeast Leamington community to coastal hazards through the development of short-term and long-term solutions.

Public Information Center 1 - Wednesday, November 27, 2019
The first Public Information Centre was held on November 27, 2019 at the Best Western Plus Leamington Hotel and Conference Centre on 566 Bevel Line Road.  The afternoon session ran from 2:00 PM to 4:00 PM, followed by an evening session from 6:30 PM to 8:30 PM.  Attendees were asked to register for the meeting in advance by calling 519-326-5761 ext. 1444 to reserve a spot at the meeting.  This was to ensure we had adequate room for all attendees.

Should you have any other questions or concerns feel free to contact Gaspare Graziano at (519) 326-5761 ext. 1303 or Allan Botham, Manager of Engineering, at ext. 1302. 

We value your feedback. By completing this comment sheet, your feedback and insights about the project was considered as the project moves forward.

Written comments were to be submitted before December 13, 2019 by: 

  • Downloading and filling out the PDF and submitting via mail or email 
  • Clicking the link below will allow you to fill out and submit comments directly to the Municiplality

PIC #1 Comment Sheet (Downloadable)


Click here for PIC #1 Presentation 

Public Information Center 2 - Wednesday, January 15, 2020
The second Public Information Centre was held on January 15, 2020 at the Best Western Plus Leamington Hotel and Conference Centre on 566 Bevel Line Road.  The afternoon session ran from 2:00 PM to 4:00 PM, followed by an evening session from 6:30 PM to 8:30 PM. Attendees were asked to register for the meeting in advance to reserve a spot. This was to ensure adequate room for all attendees. We requested that you registered by Tuesday, January 14, 2020.

Should you have any other questions or concerns feel free to contact Gaspare Graziano at 519-326-5761 ext. 1303 or Allan Botham, Manager of Engineering, at ext. 1302.

We value your feedback. By completing this comment sheet, your feedback and insights about the project was considered as the project moves forward.

Written comments were to be submitted before January 31, 2020 by:

  • Downloading and filling out the PDF and submitting via mail or email 
  • Clicking the link below will allow you to fill out and submit comments directly to the Municipality

PIC #2 Comment Sheet (Downloadable)


Click here for PIC #2 Presentation 

Public Information Center 3 - Monday, March 30, 2020 *CANCELLED*

The Municipality has taken precautionary measures and has cancelled the Public Information Centre #3 due to the concerns surrounding COVID-19 that was scheduled for Monday March 30, 2020 at the Best Western Plus Leamington Hotel and Conference Center on 566 Bevel Line Road. The Municipality will resend notifications once a new date is determined.

Should you have any other questions or concerns feel free to contact Gaspare Graziano at 519-326-5761 ext. 1303 or Allan Botham, Manager of Engineering, at ext. 1302.

Virtual Public Information Centre 3

Welcome to virtual PIC #3. Due to the concerns surrounding COVID-19 and the current restrictions, an in person PIC can not be held. Similar to prior PICs, stakeholders and residents will be given an opportunity to provide feedback, which will provide the Study Team an opportunity to gather important feedback and comments from stakeholders and residents.

The Study Team has completed the “Draft - Final” report, and it is now available along with the presentation and other information/material.

Goals of PIC #3 

The goals of this Virtual PIC are:

  • update information on floodplain mapping;
  • potential economic damages;
  • emergency access during storms;
  • summarize the results of the erosion and flooding vulnerability assessment, along with the risk to existing buildings and emergency access,
  • present and review the Draft Adaptation Options; and
  • an online survey.

The following information/material is available to download. 

Please review and provide comments via the survey. Please note the survey/comment sheet will only be available between November 24 to December 30, 2020. Following receipt of comments, the Final Report will be amended, if required, and is anticipated to be bought to Council early 2021. If you are unable to access these documents online and you require a different format, please call Mariaha at the Municipality of Leamington at 519-326-5761 ext. 1444 to make those arrangements.

Current Report Status

Leamington Administration, along with the Study Team (Zuzek Inc., SJL Engineering Inc and Foresight Consulting) will be presenting the Southeast Leamington Graduated Risk Floodplain Mapping Project Final Report to Leamington Council on February 23, 2021.

Council will be voting to receive the report on February 23, 2021. No decisions regarding the future of Southeast Leamington, or the short-term and long-term strategies to be pursued for the Southeast Leamington study area, will be made at this meeting. This meeting is to present the results of the technical study, and the public engagement process, to Council.

The Municipality will be developing formal short and long term strategies for Council to consider later in 2021. Given the magnitude of this issue, we believe that is of the utmost importance that residents be given an opportunity to address Council in person if they choose to do so. Therefore, Administration will wait until it is once again safe to gather for an in-person public meeting before bringing a report to adopt formal short and long term policies for Southeast Leamington. It appears that this may be possible late in 2021, or early 2022.
In the meantime, the Municipality will continue to pursue solutions to shoreline problems requiring immediate attention.

The following information/material is available to download. 

Council Meeting to Present Draft Final Report:
When: Tuesday, February 23, 2021 at 6:00 PM
Where: Electronic Meeting (Watch Council Live

Please note that if you wish to provide oral comments at the electronic meeting, you must register in advance by emailing clerks@leamington.ca or calling 519-326-5761 extension 1121 prior to Thursday, February 18, 2021 at 12:00 PM. Once you register, you will be contacted by the Clerk’s Department and provided information on how to make your submission at the electronic meeting by electronic participation. To participate, you will need access to a computer or tablet with internet service or a telephone.

As an alternative to attending the meeting, written correspondence may be submitted to the Clerk no later than Thursday, February 18, 2021 at 12:00 PM. Please email clerks@leamington.ca or drop it in the Leamington Municipal Building mail slot located to the right of the rear entrance off of the parking lot. The Municipal Building is located at 111 Erie Street North, Leamington, Ontario, N8H 2Z9. Please note, written correspondence may be included on the agenda which will be published on the municipal website and will form part of the public record.

 

 

Contact(s)

© 2024 The Municipality of Leamington 111 Erie Street North, Leamington, Ontario N8H 2Z9

Phone: 519-326-5761
Fax: 519-326-2481
Email: General Information

Back to top