Construction Update: Additional Road Closures for Northeast Trunk Sewer and Seacliff Drive East Reconstruction
Beginning Monday, September 21, 2026, construction staging for the Northeast Trunk Sewer and Seacliff Drive East Reconstruction Project will change, resulting in additional road closures in the project area.
As work continues on Seacliff Drive East, the next stage of construction will include the Seacliff Drive East and Bevel Line intersection, as well as Bevel Line between Seacliff Drive East and the Bayview Cemetery/Dog Park.
These closures are required for the realignment of Bevel Line to the Seacliff Drive East/Peter Avenue intersection. Due to the extensive work and installation of new traffic signals, the new intersection will remain closed until the end of the project, currently estimated for November 20, 2026, weather permitting.
Road Closures
Seacliff Drive East and Bevel Line Intersection
Limits: East of Seneca Drive to east of County Road 33
Schedule: September 21 to November 20, 2026, weather permitting
- Closed to all traffic.
- Motorists must follow the posted detour route.
Bevel Line
Limits: Between Seacliff Drive East and Bayview Cemetery/Dog Park, including the intersection
Schedule: Now through November 20, 2026, weather permitting
- Closed to all traffic.
- This section will remain closed to all traffic for the duration of the project.
- Residents and businesses must use the posted detour route.
County Road 33
Limits: Between Oak Street East and Seacliff Drive East
Schedule: Now through November 20, 2026, weather permitting
- Closed to all traffic.
- This section will remain closed to all traffic for the duration of the project.
- Residents of Sunningdale Drive, Summerville Avenue and Heathview Trail must use Clarence Avenue via Bennie Avenue.
Bayview Dog Park Access
Bayview Dog Park will remain open during construction. Due to the Seacliff Drive East/Bevel Line road closure, the dog park must be accessed from Robson Road via Bevel Line. Access to the dog park will not be available from Seacliff Drive East.
Motorists are asked to follow all posted detour signage and allow additional time when travelling through the area.
Project information will continue to be updated throughout construction. Residents can visit leamington.ca/SDER and subscribe to the project page to receive updates directly by email.
The Municipality appreciates the patience and cooperation of residents, businesses and motorists while this important infrastructure work is underway.

Figure 1:
- Seacliff Drive East: West of Bevel Line to East of County Road 33
- County Road 33: West of Bevel Line to East of County Road 33
- Between September 21 and November 2026 (weather permitting.)
Sign up for our eNews updates!
Subscribe to receive our municipal media releases, public notices, and council matters.