Update: Margaret, Audrey, Jane, Claire and Sherk Street Sewer Separation and Road Reconstruction
The Municipality of Leamington is advising residents that work on the Margaret, Audrey, Jane, Claire and Sherk Street Sewer Separation and Road Reconstruction Project will resume the week of February 23, 2026, weather permitting.
During this phase of work, the temporary road connection to Sherk Street at the east end of Claire Street will be reestablished to maintain resident access.
Jane and Claire Streets - Upcoming Work
- Sewer separation work on Jane and Claire Streets is scheduled to begin the week of February 23, 2026.
- Sewer installation on these streets is expected to be completed by mid-May.
- Concrete restoration across the project area will occur in June 2026.
- A final layer of asphalt over the entire project area is planned for mid to late June 2026, weather permitting.
The Municipality does its best to provide accurate timelines; however, all timelines are estimates and may change depending on weather and site conditions.
We appreciate the community’s continued patience and cooperation as this multi-stage project progresses.
For updates, please visit leamington.ca/MAJCS.
Contact Us
Municipality of Leamington
111 Erie Street North
Leamington, ON
N8H-2Z9
Phone: 519-326-5761
Report an Issue
Municipal Office Hours
Monday - Friday
8:30 AM to 4:30 PM
Saturday - Closed
Sunday - Closed
Sign up for our eNews updates!
Subscribe to receive our municipal media releases, public notices, and council matters.